City of Mukilteo

61st Place West Culvert Replacement

Project Description

Improvement of an existing, deficient stream crossing with a new box culvert, improving both stream function and adjacent roadway conditions. The existing 54-foot long, 24-inch diameter metal culvert will be removed and replaced with a new 40-foot long, 8.0-foot wide by 6.8-foot tall concrete box culvert. The project will also recreate approximately 320 linear feet of stream channel, construct retaining walls, relocate existing utilities, and reconstruct the existing roadway. Work involves removal of certain existing site features; clearing and grubbing; roadway and channel excavation; dewatering; structure excavation, installation, and backfill of a box culvert foundation and structure.

Date:

2023

Client:

City of Mukilteo

Location:

61st Place West; Mukilteo, WA